Progress Payments for Building in Australia: A Homeowner's Guide


A progress payment is a part-payment of your contract price, made when the build reaches a defined stage, such as slab, frame or lock-up. It is not a bill that arrives on a date the builder chooses. In every state and territory the amount has to match work that has actually been done, and that is what protects you. The best way to avoid disputes is to have a contract with clearly described stages, a builder who explains each claim, and a simple routine for checking the work before you pay.
We build, extend and renovate homes across Melbourne, so this guide leans on Victorian rules, with notes on how other states differ for owners who build interstate or invest elsewhere.
TL;DR
Progress payments are staged payments tied to completed work, not to calendar dates. Each claim should describe the stage, the amount or percentage, and what has been finished.
There is no single national schedule. Deposit limits and standard stage percentages are set state by state, so check the rules for the state where you are building.
In Victoria, a deposit is capped at 10% for contracts under $20,000 and 5% from $20,000, and the state publishes a standard schedule for common building scopes.
Before paying any claim, confirm that the stage is complete, that any required inspection has passed, and that the work matches your plans and specifications.
If you disagree with a claim, get proper advice before withholding money. Withholding the wrong way can put you in breach of your contract.
Table of Contents
What a progress payment actually is
A home build is too big to pay for at the end, and no builder can fund months of materials and trades from their own pocket. So the contract price is split into instalments. Each one is released when a physical milestone is reached.

Queensland’s building regulator describes progress payments as incremental payments made at certain stages or intervals, and says every one must be relative to the work completed. Its example: a contractor cannot claim more than 50% of the contract price, deposit included, until at least 50% of the work on site is done. Western Australia’s rules use the word “genuine”: a claim must be for work already performed or materials already supplied.
The principle is the same across the country. You pay for what exists on site, and the builder is not left out of pocket for work they have finished.
The usual stages of a residential build
Names and splits vary, but most Australian contracts follow the same physical sequence. Western Australia’s government guide describes it well:
Deposit: paid when you sign, before work starts.
Base or slab: slab and footings are complete, and drainage is usually in.
Frame: walls and roof frame are up. In Western Australia the equivalent is often called plate height, with walls erected and internal walls built.
Roof cover: the roof is on and the building is basically watertight.
Lock-up: external doors and windows are in, first-fix plumbing and electrical are run, and plastering and ceilings are installed.
Fixing or secondary finishing: tiling, cabinetry, carpentry and electrical fit-off.
Practical completion: the home is usable for its intended purpose and services are connected.
A standard new-home build usually runs through five to eight of these. A renovation or extension often has fewer, bigger stages, or stages named after the scope, such as demolition, new frame, enclosed, fit-out and completion.
There is no standardised national set of stages or percentages. The builder can propose a schedule that suits the particular work, provided each payment fairly reflects the value of what has been completed. That is why two contracts for similar houses can look different, and why you read yours closely before signing. If you want to see how schedules are laid out in practice, a set of construction payment schedule templates shows how the same stages can be arranged for different project types.
If you want the bigger picture of how a build unfolds from permits to handover, our guide to the building process for Australian homes covers it, and build timeframes in Australia shows how long each phase tends to take.
What the rules say in Victoria
If you are building in Melbourne, Consumer Affairs Victoria’s guidance is the one to know.
Deposit limits. For a domestic building contract, the deposit cannot exceed 10% of the price when the contract is under $20,000, or 5% when it is $20,000 or more. Most home extensions and new builds are well over that line, so a 5% deposit is the ceiling.
Standard stage payments. Consumer Affairs Victoria publishes a standard schedule for common scopes:
Scope of work | Base | Frame | Lock-up | Fixing |
Build to lock-up | 20% | 25% | n/a | n/a |
Build to fixing | 12% | 18% | 40% | n/a |
Build all stages | 10% | 15% | 35% | 25% |
The state advises getting legal advice if you are considering payments that differ from these. The balance of the contract price is paid at the end, once the work is finished.
Don’t pay ahead. Victoria’s consumer regulator warns against paying in advance of the work, because domestic building insurance gives limited cover and may not respond to claims on work you have paid for ahead of time.
A worked example
Say you sign a $600,000 contract in Victoria to build all stages. This is an illustration using the percentages above, not a quote:
Stage | Share | Amount |
Deposit (5% cap) | 5% | $30,000 |
Base | 10% | $60,000 |
Frame | 15% | $90,000 |
Lock-up | 35% | $210,000 |
Fixing | 25% | $150,000 |
Final balance at completion | 10% | $60,000 |
Notice where the money sits: the lock-up stage carries the largest single payment, and a meaningful balance is held back until the finish. That final balance is your leverage to get the last details right.
How other states compare
If you are buying or building as an investor outside Victoria, the numbers change.
Western Australia: the Home Building Contracts Act limits deposits to 6.5% of the contract price for contracts valued between $7,500 and $500,000.
New South Wales: the commonly cited deposit cap is 10%.
Queensland: 10% for regulated contracts over $3,300 and under $20,000, and 5% from $20,000, with some allowance for higher deposits where significant off-site work is involved.
Northern Territory: a standard schedule caps the deposit at 5%, base at 10%, frame at 20%, enclosed at 25%, fixing at 30% and practical completion at 7%, with at least 3% held for final completion after occupancy certification.
These thresholds are updated from time to time, so confirm the current figure with the state’s building regulator before you sign.
What a good progress claim looks like
The Housing Industry Association explains that, for a fixed-price contract over $20,000, each payment stage must be described in plain language, state an amount or percentage of the contract price, and be payable only after that stage of work is complete.
Queensland’s regulator adds a practical point: unclear wording about when a payment is due, or how much, is a common cause of disputes. Tie each stage to something you can see and check, such as footings poured, frame up, roof on or fit-off complete, rather than to a date. A date can arrive before the work does.
A good claim from your builder should therefore include:
The stage name exactly as it appears in your contract.
The amount or percentage due for that stage.
Any approved variations that change the amount, with the paperwork.
The due date for payment under the contract.
Once a contract is signed, the schedule is generally fixed unless a written variation changes the price. If you want to understand how contract structures affect payments, see our guide to building contract types in Australia.
How to check the work before you pay
Before each progress payment, Consumer Affairs Victoria’s checklist asks you to confirm three things:
The work has passed any inspection required under the building permit.
It matches the plans and specifications in your contract.
The stage is actually complete.
In Western Australia, the owner or an authorised person has a right to inspect during the builder’s ordinary working hours, as long as it does not unreasonably hold up the work. The point is to confirm that a slab is laid or bricks are delivered before you pay for them.
For most owners, a practical routine looks like this:
Visit the site with your claim in hand and compare what you see with the stage description.
Take dated photos of the stage as it stands.
Check that the building surveyor’s mandatory inspection for that stage has been signed off.
Ask your builder to walk you through anything you do not understand. A builder who is open about progress will be glad to.
Keep minor omissions in perspective. Western Australia’s guidance encourages common sense so small items do not stall the whole job.
The final payment is due only when the work is finished to the plans and specifications and the occupancy permit (for a new home) or the certificate of final inspection (for an extension or renovation) has been issued. Our articles on practical completion versus handover and the new home handover checklist walk through that last stage, and the building defects checklist helps you spot issues early.
If you are paying through a construction loan
Many owners fund a build with a construction loan, where the lender releases money in draws rather than you paying the builder directly. The process generally runs like this: the builder submits a claim, the lender arranges an inspection, and funds go to the builder once the work matches the claim.
Three practical things to plan for:
Fees. Lenders commonly charge a fee per draw. Brokers publish figures in the range of a few hundred dollars each, so a six-stage build can add up to a few thousand dollars. Ask your lender for their schedule of fees.
Notice. Loan conditions often require written notice before each payment date, sometimes at least seven days, and prohibit signing a payment request before the work is finished.
Cash flow. A claim is not automatically payable because it has been invoiced. There can be a gap between costs being incurred and the draw landing, and a deposit and early stages often come from your own funds first.
Lenders also tend to cap the number of draws, so a longer project may need consolidated claims. If you are weighing finance for an extension or renovation, our guide to renovation loan options in Australia helps you match a loan to the size of the job.
When you disagree with a claim
Sometimes a claim arrives that feels early, or work at a completed stage has defects. Handle it in order:
Raise it in writing straight away. Say which stage and which items you question. Uncertainty about when a payment is due is the most common cause of disputes, so be specific.
Compare against the contract. Is the stage described as complete in your schedule? Has the required inspection passed?
Get advice before withholding. Consumer Affairs Victoria advises that you should not withhold a progress payment because of defects if the stage has been completed, and to get legal advice before withholding any payment. Holding back money wrongly can put you in breach.
Use the formal channels. In Queensland, for example, the regulator can direct a contractor to rectify defective or incomplete work, and the owner should first tell the contractor in writing and allow a reasonable time to respond, such as 14 days. In Victoria, check with Consumer Affairs Victoria and the Victorian Building Authority for the process that applies to you.
Defects found after handover are covered by a separate period, which our guide to the defects liability period in Australia explains.
Questions to ask before you sign
A few minutes on the schedule before signing saves weeks of friction later:
Does every stage describe the physical work, not only a name?
Do the percentages match the state’s limits for deposits and stages?
How are variations priced and paid for, and are they in writing before the work starts?
Who inspects, and who signs off, at each stage?
What is held back until completion?
A schedule that lines up with the work on site is also the easiest way to keep your cash flow predictable. We go deeper on this in our piece on a Melbourne builder’s view of progress payment schedules.
How we manage this with you
Progress payments work best when the person managing your build is open about where the project stands. Yorcon takes on the whole process, from design and permits through to construction oversight, with a focus on clear communication and transparency. That means you are not left decoding stages and approvals alone.

We work on home extensions, renovations, design and build projects, knockdown rebuilds and heritage restorations across Melbourne. Our architectural house designs start at $15,000 and go up to $35,000 as a one-off fee. If you are planning a project and want to understand how the stages and costs would fit your home, book a free project feasibility call.
FAQ
How much deposit can a builder ask for in Victoria?
For a contract under $20,000, the deposit is capped at 10% of the price. From $20,000 it is capped at 5%. Most extensions and new homes fall into the 5% category.
Can I pay a progress payment before the stage is finished?
It is best not to. Victoria’s consumer regulator warns against paying in advance, because domestic building insurance has limited cover for work paid for ahead of time. Each payment should follow completion of the stage described in your contract.
Are progress payment percentages the same in every state?
No. Deposit caps and standard schedules differ by state and territory. For example, Western Australia caps deposits at 6.5% for contracts between $7,500 and $500,000, while Victoria uses 5% from $20,000. Always check the rules where your build is located.
Do construction loan draws work the same as paying the builder directly?
The stages are similar, but the lender usually inspects the work and pays the builder directly once it matches the claim. Expect a fee for each draw and written notice requirements, so confirm both with your lender before you sign.
What if I think a stage claim is too early?
Raise it in writing straight away and compare the claim to the stage description in your contract. Get legal advice before you withhold any payment, because holding back money incorrectly can breach the contract.
Sources
This guide draws on the published guidance of Consumer Affairs Victoria, the Queensland Building and Construction Commission, the Western Australian Department of Mines, Industry Regulation and Safety, the Northern Territory Government and the Housing Industry Association. For related reading on our own site: